Skip to main content

Logs

Logs

Purpose and when to use this record

Record chronological agency activity for operational review and reporting.

At a glance

  • Identify it by: Officer, Shift Date, On-Shift Time, and Off-Shift Time.

  • Check its business context: Officer, and Vehicle.

  • Why care: Use the agency’s approved terminology and access policy. Preserve dates, responsible personnel, case links, and audit history because these records may support official reporting or custody review.

Before you begin

You need the Brisk permission for the action you are taking on logs. If a Create, Edit, or Delete control is absent, do not work around it with another user’s account; ask an administrator to review your role.

Have valid Officer records ready first. Those selections determine where this Log belongs and which later screens can find it.

Create a Log

Create a Log only after confirming that the source document or operational event has not already been entered.

  1. Select the business context first: Officer, and Vehicle.

  2. Enter the required identifying and operational values: Officer, and Shift Date.

  3. Review On-Shift Time, Off-Shift Time, Beginning Miles, Ending Miles, and Total Miles against the source document or approved setup decision.

  4. Save the Log, then confirm Officer, Shift Date, On-Shift Time, Off-Shift Time, Vehicle, and Beginning Miles, plus the remaining screen fields on its detail page before continuing.

After saving: Use Officer, and Vehicle to interpret this Log. If it records a failure or exception, correct the source process and create a new successful event rather than rewriting the audit trail.

Delete a Log

Delete this Log only when it was entered by mistake and no downstream history depends on it. Use a reversal, void, credit, counter-adjustment, or status correction for a real event that later changed.

Before confirming, check for related Activities, and Tallies. Brisk may refuse deletion when another record depends on this one; resolve the duplicate or use the supported correction workflow instead of breaking the trail.

On the confirmation page, verify Officer, Shift Date, On-Shift Time, and Off-Shift Time. After confirmation, return to the Logs list and make sure only the intended Log was removed.

Review Log details

Use the detail page as the shared record of what this Log currently means. Verify Total Miles before relying on it for a decision.

Follow Officer, and Vehicle to determine whether the issue is on this Log or on one of those linked records.

Next check: Use Officer, and Vehicle to interpret this Log. If it records a failure or exception, correct the source process and create a new successful event rather than rewriting the audit trail.

Edit an existing Log

Edit this Log to correct or complete the same source document or operational event; use the supported reversal or follow-up workflow when the business event itself changed.

  1. Open the detail page. Compare Officer, and Vehicle with the supporting document or approved request.

  2. Recheck Total Miles. These values are most likely to change case history, custody, dispatch, official reporting, or audit review.

  3. Save the change, return to the list, and confirm that the Log now appears under the expected the identifying information shown on the screen.

After the change: Use Officer, and Vehicle to interpret this Log. If it records a failure or exception, correct the source process and create a new successful event rather than rewriting the audit trail.

Find and review logs

Brisk Logs list screen displayed with fictional documentation-demo data.
The Logs list screen in the Brisk documentation demo.

Use the Logs list to find the correct record before opening or changing it. Compare Officer, Shift Date, On-Shift Time, and Off-Shift Time. Records with similar names or numbers can still belong to different Officer, and Vehicle.

Open the Log whose Officer, Shift Date, On-Shift Time, and Off-Shift Time match the task. If it is missing, clear the list filters and recheck the identifying information shown on the screen rather than creating a replacement immediately.

Fields and business rules

Brisk stores 8 user-relevant fields for this Log, including 2 linked-record selections and 0 controlled-choice fields. Create and edit screens may hide calculated or workflow-managed values from this full reference.

Field Required What it controls
Officer Yes Sets the officer for this log entry.
Shift Date Yes The calendar date of this shift. If shift carries into a 2nd day, please use the first/starting day.
On-Shift Time No The on-shift time recorded for this log.
Off-Shift Time No The off-shift time recorded for this log.
Vehicle No Sets the vehicle that the officer is using this day.
Beginning Miles No Records the mileage of the vehicle at the beginning of the shift.
Ending Miles No Records the mileage of the vehicle at the end of the shift.
Total Miles No Records the difference between the beginning and ending mileage.

What happens next

Use Officer, and Vehicle to interpret this Log. If it records a failure or exception, correct the source process and create a new successful event rather than rewriting the audit trail.

Common mistakes and troubleshooting

  • The record will not save: Recheck Officer, and Shift Date and any message beside the field. A required related record may also be inactive or unavailable to your role.

  • The values look right but the result is wrong: Open Officer, and Vehicle from the detail page. Correct the specific relationship that is wrong instead of forcing a total or status to compensate for it.